Project SEMDA-4

Goals

The goal of the SEMDA-4 project is to adapt SEMDA-3 to the new RI-API. When possible the current SEMDA API should be preserved.

Schedule

The SEMDA-4 project has the following time schedule (state of 19.12.2025):

Date

Action

January 2026 *

Publication of the new RI-API by RI

?

SEMDA-3 TEST environment will stop working

?

Publication of the SEMDA-4 API

January - July 2026 *

Adaption of SEMDA-3 to the new RI-API

?

SEMDA-4 TEST environment ready for preliminary test

?

Production start of SEMDA-4 with new API features

July 2026 *

Shutdown of the existing (old) RI-API by Rotary International
Shutdown of SEMDA-3

*assuming RI will stick to the plan communicated in August 2025.

Test environment

Currently RI has only one test environment called UAT (User Acceptance Test) . RI will make the UAT environment with the new RI-API available to RCS on ??
At this date the SEMDA-3 TEST environment will stop working, because the API will no longer match.
The SEMDA-4 test environment will be available on ??

Production environment

When RI stops operations of the existing (old) API, SEMDA-3 must also stop operations, because the API will no longer match. This is a hard dependency and critical deadline of the project.